FEASIBILITY STUDY & ARCHITECTURAL DESIGN

The Site Plan & Feasibility Report confirms what the building envelope will be for your ADU given the local requirements and your site conditions (we also factor in constraints like septic system and HOA if relevant). Then we lay out your desired floor plan along with exterior elevations and we review the options with you live via Zoom. We can flip or mirror a standard plan to best work with your lot constraints. We can also modify our plans based on your input & requirements. We ask for a mark up with your changes to ensure we are on the same page and move swiftly through the design phase. Timing: 8-10 weeks (standard plan), 10-14 weeks (modified plan)